I was recently in Park City, Utah to teach  the Professional Scrum Foundations  course and i just got an email from one of the students. As I want to help everyone I will answer here:

If I recall from our training, you suggested teams could burn down their sprints using points or hours.  In your view is there a “better” answer in your opinion (pros/cons)?
-Pete

The first thing that we want to do is define explicitly what a burndown represents and the reason that we are creating one; i.e. what actions might we want to take. Only then can we decide what we want to measure and which is best for us.

What is a burndown?

During Sprint Planning the Development Team forecast what work it thinks it could do (selected a number of PBI’s from the Product Backlog) and created a Plan to complete them. This is known as the Sprint Backlog and it should have some measure of Remaining Work that allows the Development Team to see what they have left to do. As the Sprint Backlog (the Plan to complete the forecast PBI’s) evolves as more is known over the course of the Sprint the Remaining Work can vary and we need a way of visualizing trends so that the Development Team can take the necessary action.

A burndown is a visual representation of the Remaining Work in the Sprint Backlog as it varies over time.

What might we find?

So in order to identify actions we need to look at some things we might identify as a problem.

These are just some ideas of what might be found and are not indicative of all possible options and there are other lists of Bad Smells of the Sprint Backlog  that you can find online.

Let me reiterate, that along with the Three Questions that are part of the Daily Scrum a Burndown is just a tool to help elicit communication and understanding within the Development Team. It is not a whip for a Project Manager to crack.

What burndown is right?

So to answer the question of wither to burn down Story Points, Hours or even Test Cases I would argue that we need them all! I want to see if my tasks are on track, but I also want to make sure that I am delivering Stories as well.

The Hours Burndown

This burndown is good for helping the Development Team identify how much work is remaining in the Sprint and if they are likely to still be able to meet their Sprint Goal.

The Story Point Burndown

Good for allowing the Development Team to see if they are actually getting things Done, verses completing all of the Tasks.

The Acceptance Tests Burndown

Also a good indicator of what is going on from a delivery perspective. If you are on track for Hours, and Story Points but you have only completed 50% of your Acceptance Tests and you have 2 days left on your Sprint, what does that tell you about your quality.

Conclusion

You will need to experiment with your Scrum Teams to see which burndown is right for you, but I would suggest that you want to be able to plot all of them so that your Development Team’s have all of the relevant information for their Daily Scrum to  help them identify any issues as early as possible.

people-and-process tools-and-techniques blog agile configuration develop practices scrum

Connect with Martin Hinshelwood

If you've made it this far, it's worth connecting with our principal consultant and coach, Martin Hinshelwood, for a 30-minute 'ask me anything' call.

Our Happy Clients​

We partner with businesses across diverse industries, including finance, insurance, healthcare, pharmaceuticals, technology, engineering, transportation, hospitality, entertainment, legal, government, and military sectors.​

YearUp.org Logo
Schlumberger Logo
Lean SA Logo
Milliman Logo
Qualco Logo
New Signature Logo
Bistech Logo
Jack Links Logo
Workday Logo
Akaditi Logo
Kongsberg Maritime Logo
Ericson Logo
SuperControl Logo
Slicedbread Logo
Epic Games Logo
Flowmaster (a Mentor Graphics Company) Logo
Lockheed Martin Logo
Philips Logo
Royal Air Force Logo
New Hampshire Supreme Court Logo
Department of Work and Pensions (UK) Logo
Washington Department of Transport Logo
Ghana Police Service Logo
Nottingham County Council Logo
ALS Life Sciences Logo
Flowmaster (a Mentor Graphics Company) Logo
Akaditi Logo
SuperControl Logo
Higher Education Statistics Agency Logo

CR2