When you try to upload the default field mappings for Project Server 2013 integration with Team Foundation Server 2012 you can encounter a TF294026: The following work item field does not exist error.

TF294026: The following work item field does not exist
Figure: TF294026: The following work item field does not exist

With the message:

TF294026: The following work item field does not exist: Microsoft.VSTS.Scheduling.CompletedWork. Contact your administrator for Team Foundation Server to add this work item field.

You are unable to continue without fixing…

Applies to

  • Project Server 2013
  • Team Foundation Server 2012
  • Project Server Extensions for Team Foundation Server

Findings

Project Server requires that you have data for Remaining Work, Completed Work and Original Estimate for it to function correctly.

The Task Work Item Type only includes Remaining Work
Figure: The Task Work Item Type only includes Remaining Work

The Visual Studio Scrum Process Template however does not include these as they are not required for Scrum.

Solution

Use the instructions on Required Changes to Make When Mapping to a Team Project That Was Created From the Scrum Process Template to update the Task Work Item Type for the Visual Studio Scrum 2.0 template to add both the Completed Work and Original Estimate fields.

Warning The documentation on MSDN is currently out of date and misses two fields that need to be added. Make sure that you also add the Start and End dates.

   The number of units of work that have been spent on this task


   Initial value for Remaining Work - set once, when work begins. 



Figure: Add both Original Estimate and Completed Work

Although we are adding these fields to the Task type we are not necessarily adding them to the UI for users to fill out. We can leave them available for Project Server, while out Team Members of a Scrum Team would be blissfully ignorant of their existence.

Create a conversation around this article

Share on facebook
Share on Facebook
Share on twitter
Share on Twitter
Share on linkedin
Share on Linkdin

Want to learn more?

Check out the many training classes that we have.

No items found

Want to read more?

OUR TEAM

We believe that every company deserves high quality software delivered on a regular cadence that meets its customers needs. Our goal is to help you reduce your cycle time, improve your time to market, and minimise any organisational friction in achieving your goals.

naked Agility Limited is a professional company that offers training, coaching, mentoring, and facilitation to help people and teams evolve, integrate, and continuously improve.

We recognise the positive impact that a happy AND motivated workforce, that has purpose, has on client experience. We help change mindsets towards a people-first culture where everyone encourages others to learn and grow. The resulting divergent thinking leads to many different ideas and opportunities for the success of the organisation.