Issue [ TFS 2013 ] TF50309 when configuring features in Team Foundation Server 2013

Audience

No items found

Table of Contents

You may get a TF50309 when configuring features in Team Foundation Server 2013 and you are unable to complete the configuration.

TF50309: The following account does not have sufficient permissions to complete the operation: The following permissions are needed to perform this operation: Manage process template.

Applies to

  • Team Foundation Server 2012
  • Team Foundation Server 2013

Findings

If you are an Team Project Administrator you would expect to be able to configure the new features for your Team Project but you are prompted for the ‘Manage process template’ permission. This permission is a collection level permission and is grated automatically to Project Collection Administrators but not to Project Admins.

image
Figure: Manage process template permission

You need to configuring features in Team Foundation Server 2013 with an account that has this permission.

Solution #1 – Give one user access and configure all projects

The first solution is to have someone who is a Project Collection Administrator do the configuration. This would be awkward and boring if you have 200 Team Projects, but for one a few this is the simplest and least invasive solution.

Solution #2 – Create a new Group to give Project Admins permission

If however you have tens or hundreds of Team Project and you need to liaise with each group of users for training for the new features you may want to take a slower approach. I want to be able to delegate this permission out so that I can send an email too each of the Project owners and have them do the training and upgrade at a time that suits them.

image
Figure: Create a Project Upgraders TFS Group

You need to create a new TFS Group at the Team Collection level that will contain each of the “owners” or “upgraders” for the individual Team Projects.

image
Figure: Set the Manage process template permission only

Now that we have a group we can select it and set individual permissions. In this case we only need the manage process template permission that will allow this user to complete the configuration of the Team Project to enable the new features.

image
Figure: Add users to the new group

Now we need to add each user that we want to have this permission. It would be awesome if we could add a Team Project group in here… you know.. like the “Project Administrators” group but “[ScrumSandbox]Project Administrators” fails to resolve. Sad, but the workaround is to just add the users we want to have permission..

Create a conversation around this article

Share on facebook
Share on Facebook
Share on twitter
Share on Twitter
Share on linkedin
Share on Linkdin
Share on pinterest
Share on Pinterest

Want to learn more?

Check out the many training classes that we have.

No items found

OUR TEAM

We believe that every company deserves high quality software delivered on a regular cadence that meets its customers needs. Our goal is to help you reduce your cycle time, improve your time to market, and minimise any organisational friction in achieving your goals.

naked Agility Limited is a professional company that offers training, coaching, mentoring, and facilitation to help people and teams evolve, integrate, and continuously improve.

We recognise the positive impact that a happy AND motivated workforce, that has purpose, has on client experience. We help change mindsets towards a people-first culture where everyone encourages others to learn and grow. The resulting divergent thinking leads to many different ideas and opportunities for the success of the organisation.