Changing the Team Project Collection of the Team Build Controller

Topic(s)
Audience

No items found

Table of Contents

BuildIcon_Large

When you are doing demos or training for Team Foundation Server 2010 (TFS 2010) you may have multiple Team Project Collections (TPC) for different scenarios or process templates. You may even be attaching a pre-built TPC image so you can start from a particular point. If you try to do create a build you will find that it complains about there not being a Team Build Controller (TBC).

 

 


One thing you learn very quickly when working with TFS 2010 is that you can only attach ONE Team Build Controller to ONE Team Project Collection. This one-one relationship can cause issues if you have many Team Project Collections because there can only be one Team Project Collection configured per server.


Figure: Two Team Project Collections

This means that if you have 2 Team Project Collection you will need two serve to manage the builds. It can be the same server as your build server, but that depends on your throughput and load.

In the presentation scenario you will need to reconfigure your Team Build Controller on the fly. But how do you do this.

If you open the Team Foundation Server Administration Console you will see a “Build Configuration” node. If you select this it will show all of the configuration options for your build server on that box.

image
Figure: Team Build Configuration screen shows the Controller and any Agents running on that server

In this case this is our TFS server and we only have the Build Controller running with no Agent. We run all of the agents on another box as it takes lots of processor to do a build and we don’t want that impacting our TFS server.

In order to make the change, we need to alter the options not on the Controller instance itself, but on the Build Service Instance.

image
Figure: Change the options on the service instance

Select the “Properties” option on the Build service and then stop the service to make the changes.

image
Figure: The Build Service Properties are only available when the service is stopped

 

image
Figure: Select any server and then Project Collection you want to bind to

You need to select the server and then the Team Project Collection that you want to bind to. In fact you could have this Build Service bind to any Team Foundation Server even if the current server hosts TFS. I don’t know why you would want to, but it is possible.

Now that you have the Build Service configured to work against your new Team Project Collection the Build Controller and any Build Agents configured under it will now work for that collection.

You can now go forth and create builds…

 

Technorati Tags: ,,

Create a conversation around this article

Share on facebook
Share on Facebook
Share on twitter
Share on Twitter
Share on linkedin
Share on Linkdin

Want to learn more?

Check out the many training classes that we have.

No items found

Want to read more?

OUR TEAM

We believe that every company deserves high quality software delivered on a regular cadence that meets its customers needs. Our goal is to help you reduce your cycle time, improve your time to market, and minimise any organisational friction in achieving your goals.

naked Agility Limited is a professional company that offers training, coaching, mentoring, and facilitation to help people and teams evolve, integrate, and continuously improve.

We recognise the positive impact that a happy AND motivated workforce, that has purpose, has on client experience. We help change mindsets towards a people-first culture where everyone encourages others to learn and grow. The resulting divergent thinking leads to many different ideas and opportunities for the success of the organisation.